News

Nyack Repaving? It’s On! (Really, This Time It Is)

Updated — Nyack, 5p Fri Nov 14:

  • Work was completed from Laveta to 4th Avenue east of Brodway on 11/14.
  • There’s rain in the forecast for Monday, so work will be suspended until Wednesday 11/19.
  • Third Ave and 2nd Ave will be the next roads to be paved followed by North Broadway.

 

From Nyack-NY.gov: Street Repaving Begins (Nov 14)

Repaving for North Broadway (north of First Ave) and several side streets on Nov 14. It will only take a few days to complete.

Work will probably start with the side streets on Friday (11/14). They will start on Laveta and work south. They will not work on the weekend, so work will start up again on Monday, weather permitting.

Work on Broadway will not begin until Monday at the earliest.
All cars should be off the road by 5am on Friday, 11/14.

You May Also Like

Arts

Our roundup of events this week features fundraising galas for ArtsRock, Kula for Karma, and the Center for Safety and Change. Lafayette Theater screens...

Arts

Our roundup of events this week features a movie premiere, Nyack Fresh Market Grand Re-Opening, John Turturro at ArtsRock, Ramapo High School student show...

Arts

Our roundup of events this week features a movie premiere, the Nyack NAACP gala, the return of Nyack Restaurant week and more.

Exit mobile version