Connect with us

Hi, what are you looking for?

News

Nyack Repaving? It’s On! (Really, This Time It Is)

Updated — Nyack, 5p Fri Nov 14:

  • Work was completed from Laveta to 4th Avenue east of Brodway on 11/14.
  • There’s rain in the forecast for Monday, so work will be suspended until Wednesday 11/19.
  • Third Ave and 2nd Ave will be the next roads to be paved followed by North Broadway.

 

From Nyack-NY.gov: Street Repaving Begins (Nov 14)

Repaving for North Broadway (north of First Ave) and several side streets on Nov 14. It will only take a few days to complete.

Work will probably start with the side streets on Friday (11/14). They will start on Laveta and work south. They will not work on the weekend, so work will start up again on Monday, weather permitting.

Work on Broadway will not begin until Monday at the earliest.
All cars should be off the road by 5am on Friday, 11/14.


Nyack Farmer's Market


You May Also Like

The Villages

This week in the Villages we look at the rumor-filled and then abrupt ending of Starbucks in Nyack and what it means.

The Villages

This week in the Villages, we look delve into all the empty storefronts downtown and look back at St. Patrick's Day festivities through the...

The Villages

This week in the Villages, we look at Nyack's school board, which is expected to go into a special executive session Friday night after...

Advertisement