TZB Design? Done. Dollars? TBD

Governor Names Local Officials To Mass Transit Committee

by Vincent Pellecchia

Over a year after New York State announced a new Tappan Zee Bridge project, yesterday the New York State Thruway Authority released basic sketches and cost estimates for the three Tappan Zee Bridge replacement proposals being considered. The three bid proposals were priced at $3.14 billion, $3.99 billion and $4.06 billion, significantly lower than the state’s projections of $5.2 billion. The proposal estimates excluded $600-$800 million in additional costs. The lowest bid, submitted by Tappan Zee Constructors, won the state advisory committee’s recommendation.

However, even with the lowest estimated price tag of $3.7 billion ($3.1 billion bridge cost plus approximately $600 million in additional costs), there remains the critical unanswered question of how the state will finance this project.

Cuomo’s TZB Mass Transit Committee Includes Some Names You Will Know

On Friday, NYS Governor Andrew Cuomo named 28 people to a committee which will study mass transit solutions for the new Tappan Zee Bridge and the I-287 corridor. In addition to Thruway staff and regional transportation experts, the group includes the mayors of Nyack and South Nyack, the county executive and Rockland’s representatives in Albany.

  • Scott Baird, Nyack Chamber of Commerce
  • David Carlucci, Member, New York State Senate
  • Harriet Cornell, Chairwoman, Rockland County Legislature
  • Jan Degenshein, architect and planner
  • Tish Dubow, Mayor, Village of South Nyack
  • Ellen Jaffee, Member, New York State Assembly
  • C. Scott Vanderhoef, Rockland County Executive
  • Jen White, Mayor, Village of Nyack

On August 20, 2012, Governor Cuomo held a press conference signaling the state’s commencement of the TIFIA loan submission process. [The same day, the Governor also announced that a regional transit task force would be created.] The state’s application requested $2.9 billion in TIFIA loan funds, the maximum allowable ask for the $5.2 billion Tappan Zee Bridge project under revised TIFIA requirements. Now, with estimated bridge costs $2 billion less than the original bridge cost estimate, the state can expect to only receive 49% of the lower cost around $1.5 billion dollars. However, without a financing plan for the bridge, the federal government will not move forward with the state’s TIFIA loan application. TIFIA requirements very explicitly state a financing plan is necessary.

Additionally, the Authority’s financial house is not yet in order making it a questionable candidate for TIFIA loan approval. The Authority has indicated several cost efficiency and revenue generating measures it plans to undertake to shore up its credit outlook. One such measure is a proposed 45% commercial toll increase which is needed for the Authority’s existing capital budget. The revenue generated from this proposed increase would not be used to directly finance the new bridge, but would indirectly impact the possibility of low cost borrowing for the new project. In June of this year, both Moody’s and S&P downgraded the credit outlook for the Authority to negative potentially leading to higher interest rates in the absence of sustainable revenue streams from sources such as tolls.

The public is still waiting for the projected toll increase for passenger vehicles. Now that the estimates for the bridge have been released, this projection should be forthcoming, as well as the financing plan.

Vincent Pellecchia writes about regional transportation issues for the Tri-state Transportation Campaign at blog.tstc.org

 




You May Also Like

Arts

Healing & Empowerment Saturday, November 23 from 11:00am-Noon, Nyack Center In response to the recent wave of hateful messages targeting people of color, immigrants,...

Arts

Pasta Night at Flours Pasta & Bakeshop Friday, November 15 from 6:00-8:30pm, 11 New Main St, Haverstraw Flours Pasta and Bake shop, a Nyack...

Arts

Sniff A Pickle Reception for Marisol Diaz & Bill Batson Friday, December 6, 6:00 – 8:00pm Illustrations & Designs by Amarettogirl (a.k.a.) Marisol Diaz...