Nyack Library Construction Update — May 7

Project Manager Stephen Hoefer writes in his blog, “New Chapter, The Nyack Library Expansion,” that crane and steel will be delivered on May 12. “With this delivery you will see the construction site buzz with activity as the steel framing goes up and the steel decking goes down. It should take approximately 2-3 weeks for the iron workers to erect the skeleton of the building.”